By Andy Hunter, Director, Evolve Energy Green Solutions
I am often asked whether the two main electricity relief schemes for process plants are the same thing. They are not. One of them, the British Industrial Competitiveness Scheme (BICS), closes at 11:59pm on Monday 30th November 2026.
What BICS does
BICS exempts eligible manufacturers from the indirect costs of the Renewables Obligation, the Feed-in Tariff and the Capacity Market. The government says it will reduce electricity costs by up to £40 per megawatt hour. Renewables Obligation and Feed-in Tariff relief is due to start in April 2027, and Capacity Market relief in October 2027. The scheme applies in Great Britain only.
Only electricity imported from the grid is in scope. On-site generation, such as solar or combined heat and power, is not. Where a site makes both eligible and ineligible products, the exemption is pro-rated: 100% if 50% or more of the site’s grid electricity is used for eligible manufacturing, 50% if the share is more than 25% but less than 50%, and none if it is 25% or less.
Who can apply
A business must meet all four tests: registration at Companies House; an eligible four-digit Standard Industrial Classification (SIC) code on the official list; manufacture of an eligible product in Great Britain, classified by a Harmonised System (HS) code; and at least 33 megawatt hours of grid-supplied electricity a year at the manufacturing site. That last test is evidenced by more than 16.5 megawatt hours in the most recent six consecutive months available within the last 12 months.
Many chemicals, plastics, glass and metals activities are on the official SIC list, but not every activity in those industries qualifies, and the product must also be on the HS list. Only one of a company’s SIC codes needs to be eligible, but it must accurately reflect the site. The government has published both lists and an online eligibility checker.
What to have ready
Applications are made online, one per company, and cannot be amended once submitted. You will need a GOV.UK One Login account, your Companies House number, each Great Britain site’s details and Meter Point Administration Numbers, six months of electricity consumption evidence for each relevant meter, and six months of evidence that eligible products are made at the site. Extra evidence is needed for landlord or shared-meter supplies, private wire arrangements, or existing relief under another scheme. Paper applications must also arrive by 11:59pm on 30th November.
The Energy Intensive Industries scheme
The Energy Intensive Industries (EII) scheme, part of the British Industry Supercharger, remains open. It is narrower and usually offers more support.
To qualify, a business must manufacture a product in the UK in an eligible NACE sector, and its electricity costs must be at least 20% of its gross value added over the relevant period. A successful applicant receives an EII certificate. For the share of electricity used to make an eligible product, that certificate provides a full exemption from the indirect costs of Contracts for Difference, the Renewables Obligation, the Feed-in Tariff and the Capacity Market. From 1 April 2026 it also entitles the holder to apply for 90% compensation on the corresponding network charges (TNUoS, DUoS and BSUoS). The government estimates total support under this package at about £65 to £87 per megawatt hour.
Apply by sending the official GOV.UK forms to energyintensiveindustries@businessandtrade.gov.uk. Certificates expire and need to be renewed, but there is no BICS-style closing date.
How the two schemes relate
BICS does not exempt Contracts for Difference and does not compensate network charges. EII does both, which is why the Supercharger generally provides higher support. A business already on the Supercharger may still apply for BICS, but it cannot receive relief for the same activity under both. Any BICS exemption applies only to the share of electricity not already covered by an EII certificate. If the same activity qualifies for both, official guidance is that the Supercharger is usually the better option, and switching is likely to leave a gap in support.
When we speak to clients about these schemes, they are usually overwhelmed. Most do not have the time to work through the guidance, and the path is not always clear. That is why we help and support them through it, from checking eligibility to getting the application in.
If a site may meet the BICS tests and is not already fully covered by an EII certificate, the checker and application service are on GOV.UK. The deadline is 11:59pm on Monday 30th November.
Andy Hunter is Director of Evolve Energy Green Solutions, a family-run commercial utility consultancy working UK-wide. He has worked in the commercial energy sector for over 20 years.